Solar Case Study - Something Different wholesale
CASE STUDY
The installation of this 1.1 mWh system in Swansea, provides a simple and effective way to reduce energy use.
Something Different Wholesale in Swansea, have grown rapidly in the past 22 years and is recognised as one of the UK's leading wholesale giftware suppliers. They have 2 large factories which store their products and houses their teams and offices.
Jane Wallace-Jones the CEO at S.D.W. recognised the need to reduce the factories carbon reduction and approached Power on Demand a solar system to be installed.
The system installed consists of
2037 Bifacial Panels,
9 Solis Inverters (various sizes)
Tigo Control systems
Reunsol Rail
Then energy produced is available to the Grid and the warehouse, with a annal consumption of 961.220 kWh PA
The CO2 Emissions avoided are 630,540 kg PA
Our Process
Something Different Wholesale approached us regarding installing a solar system to reduce their energy costs and sell energy back to the grid. The site has 2 large warehouses, operates 6 days a week, 52 weeks per year. It was therefore important to consider both its energy use and environmental impact. Their energy consumption was a major contributor to this, given the constant and continued operation of the site.
Power on Demand Ltd engaged with the site team to assess the most appropriate solution, including:
- Full site survey of the roof space
- Engagement with the site team understand operational activities and assess needs
- 1/2 hourly data was obtained, enabling us to calculate a business case covering capital cost, return on investment, finance options and carbon/energy savings
- DNO application, to obtain permission to connect to the grid
- Installation programme timescales
- HV Connections including new manufactured panel boards
- Arranged for the sale of the surplus electricity to go back to the grid
Our Solution
From our assessment, our team provided a full robust business case for the Solar installation. The site would benefit from:
- More than 961,2 mWh in electricity annually.
- Reduction of the site’s carbon footprint by over 630,540kg PA
Project Installation
The full installation of the project, took four months to complete, with our team managing a full turnkey solution process, working around the existing operation without disruption, enabling the site to operate in ‘a business as usual manner’.
TIGO SYSTEM
It is an advanced add-on retrofit optimisation solution. Additionally it monitor modules and provide a rapid shutdown.
Features:
- A Module level optimisation for increased energy yield.
- Manual or automatic module-level shutdown.
- Module level monitoring for energy production tracking and system
- Smart commissioning - with android or IOS

Chevron Canary Wharf
The project amounted to over 1,600 fittings on two floors. The building is in use 24/7 sporadically. Power on Demand Ltd engaged with Chevron and Sodexo to provide the most appropriate lighting solution. Chevron’s key requirements were:
